tsys9 identified: OptiPlex 7080 / i5-10500 PVE node, RAPL live (#826)
ci / audit (push) Successful in 23s
ci / audit (push) Successful in 23s
https://projects.knownelement.com/issues/826#note-3
This commit is contained in:
@@ -60,8 +60,9 @@ for watts.
|
|||||||
update iDRAC6 firmware on tsys6 if DCMI commands fail.
|
update iDRAC6 firmware on tsys6 if DCMI commands fail.
|
||||||
4. tsys5 (T7500): budget a metered PDU or smart plug — no software path
|
4. tsys5 (T7500): budget a metered PDU or smart plug — no software path
|
||||||
exists (fits the planned UPS re-cabling: put tsys5 on the metered leg).
|
exists (fits the planned UPS re-cabling: put tsys5 on the metered leg).
|
||||||
5. tsys9: run `dmidecode -t system` + `ls /sys/class/powercap` — that pair
|
5. tsys9 RESOLVED (2026-09-06): OptiPlex 7080, i5-10500, live PVE 9.2.5 node
|
||||||
answers both its AMT and RAPL questions; report back.
|
(100.101.158.76 — runs pfv-netinfra-02 + k8s wnode-tsys9); RAPL present —
|
||||||
|
include it in the RAPL exporter wave.
|
||||||
6. UPS plan alignment: since only tsys6/7 (BMC) + RAPL hosts give per-node
|
6. UPS plan alignment: since only tsys6/7 (BMC) + RAPL hosts give per-node
|
||||||
watts, keep the metered UPS leg feeding the gear you most need wall-watts
|
watts, keep the metered UPS leg feeding the gear you most need wall-watts
|
||||||
for; per-node software telemetry covers the rest.
|
for; per-node software telemetry covers the rest.
|
||||||
|
|||||||