1.9 KiB
1.9 KiB
[toc]
Introduction to December 2024 Plan
The below list represents my exit from COO (and all reporting functions) critical path by December 21st.
The goal, is that after December 21st, I will invert my weekly time allocation :
- Current time allocation: 90% COO, 10% CTO
- Desired time allocation: 90% CTO, 10% COO
Redmine will be the data oracle to determine if that goal is successful.
Milestones
todo capture
-
Due: 12/5/2024 by midnight.
-
Status: in progress. About 80% done.
-
Capture all links from wallabag/linkding/Joplin to Redmine as todo items.
-
Setup appropriate milestones / sprints / trackers / workflows etc
Personal velocity / organization tasks
- Finish personal velocity multiplier misc tasks / projects (as captured in Redmine): https://projects.knownelement.com/versions/6
Ensure all my work is being captured for later monetization
- Finalize streaming setup: https://projects.knownelement.com/issues/75
- Get a CMS/publishing workflow setup for my website: https://projects.knownelement.com/issues/143
Revgen (hourly and sponsorship)
https://projects.knownelement.com/projects/the-reachableceo-show/roadmap
- rework resume (done) : https://projects.knownelement.com/issues/144
- setup profiles on all job seeking platforms and upload re worked resume (done) : https://projects.knownelement.com/issues/145
- Streamline inbound sales lead qualification process (done) : https://projects.knownelement.com/issues/146
- profiles for sponsorship platforms (not started) https://projects.knownelement.com/versions/4
- self hosted sponsorship website configuration (not started other than deplolying worpdress and some plugins): https://projects.knownelement.com/issues/147 and
Application deployment
- From the comprehensive todo list in Redmine, ensure complete list of needed applications for coolify-it deployment are captured.
- Deploy those applications into the coolify it instance.