ReadySetGit/Status-Report.md

165 lines
7.8 KiB
Markdown
Raw Normal View History

2023-03-24 16:29:16 +00:00
<!-- markdownlint-disable-next-line first-line-h1 -->
_TODO: Copy this file for each status report. Fill in the information
2018-08-14 21:52:57 +00:00
below. Email a notification to stakeholders when this report is made
2023-03-24 16:29:16 +00:00
available._
2018-08-14 21:52:57 +00:00
2023-03-24 16:29:16 +00:00
_TODO: Edit the rows in the following table. In some rows, multiple
examples are given, you should select/edit only one._
2018-08-14 21:52:57 +00:00
2018-08-23 17:23:45 +00:00
##### Project
2018-08-24 10:30:24 +00:00
2018-08-23 17:23:45 +00:00
::[PROJECT-NAME](Home)
2018-08-14 21:52:57 +00:00
2018-08-24 10:30:24 +00:00
##### Status Report Date
2018-08-14 21:52:57 +00:00
::YEAR/MONTH/DAY
2018-08-24 10:30:24 +00:00
##### Next Internal Release Number
2018-08-14 21:52:57 +00:00
::X.Y.Z
2018-08-24 10:30:24 +00:00
##### Release Date
2018-08-14 21:52:57 +00:00
- ::Original estimate: YEAR/MONTH/DAY
- ::Current estimate: YEAR/MONTH/DAY
- ::Change Since Last Report: No change
- ::Change Since Last Report: Slipped 2 days
- ::Change Since Last Report: Saved 4 days
2021-08-01 13:15:57 +00:00
##### Open Issues (needing development)
2018-08-24 10:30:24 +00:00
2018-08-14 21:52:57 +00:00
- ::[17 defects](ISSUE-TRACKER-QUERY)
2021-08-01 13:15:57 +00:00
- ::[8 enhancements](#tbd)
2018-08-14 21:52:57 +00:00
2021-08-01 13:15:57 +00:00
##### Resolved Issues (pending verification)
2018-08-24 10:30:24 +00:00
2021-08-01 13:15:57 +00:00
- ::[0 defects](#tbd)
- ::[2 enhancements](#tbd)
2018-08-14 21:52:57 +00:00
2021-08-01 13:15:57 +00:00
##### Closed Issues
2018-08-24 10:30:24 +00:00
2021-08-01 13:15:57 +00:00
- ::[34 defects](#tbd)
- ::[3 enhancements](#tbd)
2018-08-14 21:52:57 +00:00
2021-08-01 13:15:57 +00:00
##### Resources used this period
2018-08-24 10:30:24 +00:00
2018-08-23 17:23:45 +00:00
- ::PERSON-NAME: 18 hours.
- ::PERSON-NAME: 15 hours.
- ::PERSON-NAME: 10 hours.
- ::PERSON-NAME: 12 hours.
2018-08-14 21:52:57 +00:00
2021-08-01 13:15:57 +00:00
##### Status Summary
2018-08-24 10:30:24 +00:00
2018-08-14 21:52:57 +00:00
- ::Project completed. This is the final status report.
- ::Low risk. Project on track.
- ::Medium risk. Problems are being dealt with.
- ::High risk. Advice from management and stakeholders needed.
- ::Project canceled. This is the final status report.
2018-08-23 17:23:45 +00:00
##### Related Documents
2018-08-24 10:30:24 +00:00
2018-08-23 17:23:45 +00:00
- [Project plan](Project-Plan) > [Resource needs](Resource-Needs)
2018-08-14 21:52:57 +00:00
- [QA plan](QA-Plan)
- [Glossary](Glossary)
2018-08-24 10:30:24 +00:00
2018-08-14 21:52:57 +00:00
---
**Process impact:** This helps keep stakeholders informed of project
status so that they may correctly set expectations. Reasoned
explanations of slight changes in schedule are much better than major
unexplained slips.
### Detailed Status
TODO: Provide 1-4 paragraphs describing what has happened on this
project. The text below is just an example, replace it with your own
words.
::This week we focused on...
::Two major problems have been uncovered...
2018-08-24 10:30:24 +00:00
::We are approximately 30% of the way through the project plan, and running about 2 days ahead of schedule...
2018-08-14 21:52:57 +00:00
::The reason for the change in estimated release date is...
2018-08-24 10:30:24 +00:00
::To stay on schedule, we have slipped enhancements [issue92](ISSUE-TRACKER-URL),
2018-08-14 21:52:57 +00:00
[issue 101](ISSUE-TRACKER-URL), and [issue 129](ISSUE-TRACKER-URL) to a later
release. These issues were selected because ...
### Risk Management
2023-03-24 16:29:16 +00:00
_TODO: List 3-10 of the top project risks that are still outstanding.
2018-08-14 21:52:57 +00:00
This list may be an **updated** copy from [project plan](Project-Plan.html#Risk-Management)
2023-03-24 16:29:16 +00:00
or a previous status report._
2018-08-14 21:52:57 +00:00
- ::We could face major difficulties with the technology chosen for
this project. HOW TO AVOID/MITIGATE?
- ::We could have low quality that demands significant rework. HOW TO
AVOID/MITIGATE?
- ::We could incorrectly assess our progress until it is too late
to react. HOW TO AVOID/MITIGATE?
- ::There may be a mis-alignment of stakeholder goals or expectations.
HOW TO AVOID/MITIGATE?
### Upcoming Activity
2023-03-24 16:29:16 +00:00
_TODO: Provide a few bullets describing what you will do between now and
2018-08-14 21:52:57 +00:00
the next status report. The text below is just an example, replace it
with your own words. Link to open issues in the issue tracker whenever
2023-03-24 16:29:16 +00:00
possible._
2018-08-14 21:52:57 +00:00
- ::Fix [issue 130](ISSUE-TRACKER-URL)
- ::Fix [issue 133](ISSUE-TRACKER-URL)
2021-08-01 13:15:57 +00:00
- ::Verify [issue 102](ISSUE-TRACKER-URL), [issue 103](ISSUE-TRACKER-URL),
2023-03-24 16:29:16 +00:00
[issue 107](ISSUE-TRACKER-URL), and [issue 109](ISSUE-TRACKER-URL)
2018-08-14 21:52:57 +00:00
- ::Conduct regular team meeting: Tuesday, 1 hour
- ::Conduct review meeting: Wednesday, 2 hours
- ::Make major progress on COMPONENT
- ::Work through next release checklist
- ::Continue functional testing
- ::Revise our integration procedure
- ::Release version X.Y.Z
### Tracking to Plan
2023-03-24 16:29:16 +00:00
_TODO: Copy the Work Breakdown Structure from the [project plan](Project-Plan) and paste it here.
Add a new column for actual effort spent so far by all team members._
2018-08-14 21:52:57 +00:00
| Step | Description | Planned Hours | Spent To-Date |
2023-03-24 16:29:16 +00:00
| ---------- | -------------------------------------------------------------------- | ------------- | ------------- |
2018-08-14 21:52:57 +00:00
| ::1. | ::Preparation | | |
| ::1.1. | ::Developer training | ::30h | ::0h |
| ::2. | ::Inception | | |
| ::2.1. | ::Requirements gathering | ::30h | ::0h |
| ::2.2. | ::Requirements specification | ::20h | ::0h |
| ::2.3. | ::Requirements validation | ::10h | ::0h |
| ::3. | ::Elaboration | | |
2023-03-24 16:29:16 +00:00
| ::3.1. | ::High-level design | ::5h | ::0h |
2018-08-14 21:52:57 +00:00
| ::3.2. | ::Low-level design (break down by component) | | |
| ::3.2.A. | ::Object design | ::10h | ::0h |
| ::3.2.B. | ::User interface design | ::10h | ::0h |
| ::3.2.C. | ::Database design | ::3h | ::0h |
| ::3.3. | ::Design review and evaluation | ::5h | ::0h |
| ::4. | ::Construction | | |
| ::4.1.A. | ::System implementation | | |
| ::4.1.A.1. | ::Implement Component 1 | ::25h | ::0h |
| ::4.1.A.2. | ::Implement Component 2 | ::25h | ::0h |
| ::4.1.A.3. | ::Implement Component 3 | ::25h | ::0h |
| ::4.1.A.4. | ::Implement Component 4 | ::25h | ::0h |
| ::4.1.A.5. | ::Integrate Components (mostly done during component implementation) | ::5h | ::0h |
| ::4.1.B. | ::Technical documentation (break down by component) | ::10h | ::0h |
| ::4.1.C. | ::User documentation (break down by component) | ::10h | ::0h |
| ::4.1.D. | ::Testing | | |
| ::4.1.D.1. | ::Test planning | ::10h | ::0h |
| ::4.1.D.2. | ::Test code implementation (break down by component) | ::30h | ::0h |
| ::4.1.D.3. | ::Test execution | ::10h | ::0h |
| ::4.2. | ::Implementation review and evaluation | ::15h | ::0h |
| ::5. | ::Transition | | |
| ::5.A. | ::Release packaging | ::3h | ::0h |
| 5.B. | ::Documentation for other groups | ::3h | ::0h |
| ::6. | ::Reflection | | |
| ::6.1. | ::Postmortem report | ::10h | ::0h |
| | Total | ::329 hours | |