@ -46,6 +46,54 @@ Responsibilities of the project manager including:
|
||||
|
||||
## Sprint Calendar
|
||||
|
||||
Certain process points are regularly scheduled in the sprint cycle.
|
||||
|
||||
### Sprints by Release
|
||||
|
||||
Allocation of work among sprints should be planned relative to release
|
||||
goals and milestones. As a general guideline, higher-risk work (large
|
||||
new features which may carry new defects, major refactoring, design
|
||||
changes with uncertain effects on usability) should be allocated to
|
||||
earlier sprints, allowing for time in later sprints to ensure stability.
|
||||
|
||||
| Sprint | Focus |
|
||||
|:------:|:--------------------------------------------------------|
|
||||
| __1__ | Prototyping, design, experimentation. |
|
||||
| __2__ | New features, refinements, enhancements. |
|
||||
| __3__ | Feature completion, low-risk enhancements, bug fixing. |
|
||||
| __4__ | Stability & quality assurance. |
|
||||
|
||||
### Sprints 1-3
|
||||
|
||||
The first three sprints of a release are primarily centered around
|
||||
development work, with regular acceptance testing in the third
|
||||
week. During this third week, the top priority should be passing
|
||||
acceptance testing (e.g. by resolving any blockers found); any
|
||||
resources not needed for this effort should be used to begin work
|
||||
for the subsequent sprint.
|
||||
|
||||
| Week | Mon | Tue | Wed | Thu | Fri |
|
||||
|:-----:|:-------------------------:|:------:|:---:|:----------------------------:|:-----------:|
|
||||
| __1__ | Sprint plan | Tag-up | | | |
|
||||
| __2__ | | Tag-up | | | Code freeze |
|
||||
| __3__ | Sprint acceptance testing | Triage | | _Sprint acceptance testing*_ | Ship |
|
||||
|
||||
* If necessary.
|
||||
|
||||
### Sprint 4
|
||||
|
||||
The software must be stable at the end of the fourth sprint; because of
|
||||
this, the fourth sprint is scheduled differently, with a heightened
|
||||
emphasis on testing.
|
||||
|
||||
| | Mon | Tue | Wed | Thu | Fri |
|
||||
|-------:|:-------------------------:|:------:|:---:|:----------------------------:|:-----------:|
|
||||
| Week 1 | Sprint plan | Tag-up | | | Code freeze |
|
||||
| Week 2 | Acceptance testing | Triage | | | |
|
||||
| Week 3 | _Acceptance testing*_ | Triage | | _Acceptance testing*_ | Ship |
|
||||
|
||||
* If necessary.
|
||||
|
||||
## Process Points
|
||||
|
||||
* __Sprint plan.__ Project manager allocates issues based on
|
||||
@ -101,7 +149,7 @@ Responsibilities of the project manager including:
|
||||
testing and deploy that version. (Only true if acceptance
|
||||
testing has passed by this point; if acceptance testing has not
|
||||
been passed, will need to make ad hoc decisions with stakeholders,
|
||||
e.g. “extend the sprint” or “defer shipment until end of next
|
||||
sprint.”)
|
||||
e.g. "extend the sprint" or "defer shipment until end of next
|
||||
sprint.")
|
||||
|
||||
|
||||
|