@ -46,6 +46,54 @@ Responsibilities of the project manager including:
## Sprint Calendar
Certain process points are regularly scheduled in the sprint cycle.
### Sprints by Release
Allocation of work among sprints should be planned relative to release
goals and milestones. As a general guideline, higher-risk work (large
new features which may carry new defects, major refactoring, design
changes with uncertain effects on usability) should be allocated to
earlier sprints, allowing for time in later sprints to ensure stability.
| Sprint | Focus |
|:------:|:--------------------------------------------------------|
| __1__ | Prototyping, design, experimentation. |
| __2__ | New features, refinements, enhancements. |
| __3__ | Feature completion, low-risk enhancements, bug fixing. |
| __4__ | Stability & quality assurance. |
### Sprints 1-3
The first three sprints of a release are primarily centered around
development work, with regular acceptance testing in the third
week. During this third week, the top priority should be passing
acceptance testing (e.g. by resolving any blockers found); any
resources not needed for this effort should be used to begin work
for the subsequent sprint.
| Week | Mon | Tue | Wed | Thu | Fri |
|:-----:|:-------------------------:|:------:|:---:|:----------------------------:|:-----------:|
| __1__ | Sprint plan | Tag-up | | | |
| __2__ | | Tag-up | | | Code freeze |
| __3__ | Sprint acceptance testing | Triage | | _Sprint acceptance testing*_ | Ship |
* If necessary.
### Sprint 4
The software must be stable at the end of the fourth sprint; because of
this, the fourth sprint is scheduled differently, with a heightened
emphasis on testing.
| | Mon | Tue | Wed | Thu | Fri |
|-------:|:-------------------------:|:------:|:---:|:----------------------------:|:-----------:|
| Week 1 | Sprint plan | Tag-up | | | Code freeze |
| Week 2 | Acceptance testing | Triage | | | |
| Week 3 | _Acceptance testing*_ | Triage | | _Acceptance testing*_ | Ship |
* If necessary.
## Process Points
* __Sprint plan.__ Project manager allocates issues based on
@ -101,7 +149,7 @@ Responsibilities of the project manager including:
testing and deploy that version. (Only true if acceptance
testing has passed by this point; if acceptance testing has not
been passed, will need to make ad hoc decisions with stakeholders,
e.g. “extend the sprint” or “defer shipment until end of next
sprint.)
e.g. "extend the sprint" or "defer shipment until end of next
sprint.")